Mumbai-Ahmedabad Bullet Train Achieves First Tunnel Breakthrough

Jul 11, 2025

Mumbai-Ahmedabad Bullet Train Achieves First Tunnel Breakthrough

The Mumbai-Ahmedabad High-Speed Rail (MAHSR) project has achieved a major milestone with the successful breakthrough of a 2.7-kilometre tunnel section. The National High Speed Rail Corporation Limited (NHSRCL) announced this as the first breakthrough in the 21-kilometre tunnel between Bandra-Kurla Complex (BKC), Mumbai, and Shilphata, Thane.

This tunnel is a critical segment of India’s first bullet train corridor. Out of the total 21 km, 16 km will be constructed using Tunnel Boring Machines (TBMs), while the remaining 5 km – especially between Shilphata and Ghansoli – is being built using the New Austrian Tunnelling Method (NATM). The project also includes a 7-km undersea tunnel section beneath Thane Creek, a first-of-its-kind challenge in Indian tunneling history.

To speed up progress, an Additional Driven Intermediate Tunnel (ADIT) was constructed, allowing excavation from both Ghansoli and Shilphata sides simultaneously. So far, around 1.62 km has been excavated from Shilphata, taking the total NATM progress to 4.3 km.

Advanced safety systems have been implemented at the site, including ground settlement markers, piezometers, inclinometers, strain gauges, and biometric access controls to protect surrounding infrastructure and communities.

While the NATM portion has made significant progress, Tunnel Boring Machines for the remaining 16-km stretch are yet to be delivered, though all launch shafts and supporting equipment are ready.

The ₹1.08 lakh crore project is being funded by the Union Government (₹10,000 crore), the states of Gujarat and Maharashtra (₹5,000 crore each), and a low-interest loan from Japan at just 0.1%.

This milestone marks a significant leap forward in India's ambition to introduce high-speed rail infrastructure, promising faster, safer, and more efficient intercity travel in the near future.

Source: https://infra.economictimes.indiatimes.com/news/railways/mumbai-ahmedabad-bullet-train-tunnel-breakthrough-a-milestone-in-high-speed-rail/122370132

Related News

Mysuru’s 105.5 km Peripheral Ring Road Project Enters Land-Acquisition Phase: MDA Prepares for Major Urban Expansion

Mysuru’s 105.5 km Peripheral Ring Road Project Enters Land-Acquisition Phase: MDA Prepares for Major Urban Expansion

The Mysuru Development Authority (MDA) begins land acquisition efforts for the 105.5 km Peripheral Ring Road (PRR), planning a 200-foot wide, six-lane corridor with service roads and surrounding township over 27,500 acres to decongest the city and catalyze regional growth.

11/17/2025
Jinkushal Industries Secures $5 Million Repeat Export Order for HexL 420X Backhoe Loaders

Jinkushal Industries Secures $5 Million Repeat Export Order for HexL 420X Backhoe Loaders

Jinkushal Industries (JKIPL) wins a USD 5 million repeat export order from North America for 100 HexL 420X Backhoe Loaders, marking a key milestone in India’s export-led construction equipment growth story.

11/12/2025
BMC, MRIDC to Build Rs 805-Crore Cable-Stayed Y-Bridge Flyover in Byculla

BMC, MRIDC to Build Rs 805-Crore Cable-Stayed Y-Bridge Flyover in Byculla

The BMC and MRIDC have invited bids for a Rs 805-crore cable-stayed flyover linking the historic Y-Bridge in Byculla with the JJ Flyover, aimed at decongesting South Mumbai’s traffic corridors

10/29/2025
Adani’s ITD Cementation Wins ₹1,644 Crore Pune Metro Contract for Swargate–Katraj Underground Line

Adani’s ITD Cementation Wins ₹1,644 Crore Pune Metro Contract for Swargate–Katraj Underground Line

Maha-Metro has awarded a ₹1,644 crore contract to Adani Group’s ITD Cementation India Ltd for the 5.46 km Swargate–Katraj underground Pune Metro stretch. The project will include three stations and boost connectivity in southern Pune.

10/27/2025
KPIL Order Inflows Near ₹15,000 Crore in FY26, Up 25% YoY

KPIL Order Inflows Near ₹15,000 Crore in FY26, Up 25% YoY

KPIL reports strong order inflows nearing ₹15,000 crore in FY26, marking 25% YoY growth driven by robust demand in power transmission and building projects.

10/24/2025